Project Overview

Lampson International was tasked with replacing a reactor and regenerator as part of a major refinery upgrade at Chevron Richmond. The operation was completed during a 70-day shutdown window to minimize production downtime.

Project Challenges & Solutions

  • Used Transi-Lift LTL-2600 with 340′ boom and 160′ jib
  • Regenerator lift: 950,000 lbs | Reactor lift: 550,000 lbs
  • Assembly and disassembly performed over an H2S flare line 40′ above ground
  • Lift executed safely at 85% capacity of two M2250s and one M999 cranes

Key Equipment Used

  • Transi-Lift LTL-2600
  • M2250 and M999 cranes

Project Details

Categories:
Client: Chevron
Location: Richmond, CA
Completed: 2016