Lampson International supported the GCC Cement Dacotah Plant in Rapid City, SD, working for the CCC Group on a major plant addition. A Manitowoc 18000 crane, equipped with a 180’ main boom and a 230’ luffing jib, was on site for the 12-month project.

Project Overview
Project Challenges & Solutions
- Overhead obstructions limited ground assembly of the main boom and luffing jib
- Assisted by Manitowoc to design an in-air assembly procedure
- LinkBelt 248 Crawler Crane supported 120’ of luffing jib
- LinkBelt 8065 RTC assisted with remaining boom section assembly
- In-air assembly completed in approximately 12 hours
Key Equipment Used
- Manitowoc 18000 crane with luffing jib attachment
- LinkBelt 248 Crawler Crane
- LinkBelt 8065 RTC
PROJECT DETAILS
| Categories: | |
| Client: | CCC Group |
| Location: | Rapid City, SD |
| Completed: | 2017 |