In 2019, Lampson International teamed with Apollo Inc. to plan and execute the lift and placement of the Duportail Bridge spans in Richland, Washington. The project leveraged the Lampson Transi-Lift LTL-1100 with 380’ of boom and 1,600 kips of counterweight to manage the heavy and precise lifts required.

Project Overview
Key Operations & Capabilities
- Largest girder measured 175’ in length and weighed 228,000 pounds with rigging
- Longest reach achieved was 320’
- Supplied concrete test weights to construct a pad 20’ into the Yakima River for optimal crane placement
- Set 50 girders in four weeks, then dismantled and removed the crane in two weeks
Project Overview
- Managed lifts under constantly changing water levels
- Integrated engineering, rigging, and heavy lift expertise for safe operations
- Delivered the project on schedule, meeting all client requirements
PROJECT DETAILS
| Categories: | |
| Client: | Apollo, Inc. |
| Location: | Richland, Washington |
| Completed: | 2019 |